A photovoltaic power station, also known as a solar park, solar farm, or solar power plant, is a large-scale grid-connected photovoltaic power system (PV system) designed for the supply of merchant power. They are different from most building-mounted and other decentralized solar power because they supply power at the Public utility level, rather than to a local user or users. Utility-scale solar is sometimes used to describe this type of project.
This approach differs from concentrated solar power, the other major large-scale solar generation technology, which uses heat to drive a variety of conventional generator systems. Both approaches have their own advantages and disadvantages, but to date, for a variety of reasons, photovoltaic technology has seen much wider use. , about 97% of utility-scale solar power capacity was PV.
In some countries, the nameplate capacity of photovoltaic power stations is rated in megawatt-peak (MWp), which refers to the solar array's theoretical maximum Direct current power output. In other countries, the manufacturer states the surface and the efficiency. However, Canada, Japan, Spain, and the United States often specify using the converted lower nominal power output in watt-peak AC, a measure more directly comparable to other forms of power generation. Most solar parks are developed at a scale of at least 1 MWp. As of 2018, the world's largest operating photovoltaic power stations surpassed 1 gigawatt. At the end of 2019, about 9,000 solar farms were larger than 4 MWAC (utility scale), with a combined capacity of over 220 GWAC.
Most of the existing large-scale photovoltaic power stations are owned and operated by independent power producers, but the involvement of community and utility-owned projects is increasing. Previously, almost all were supported at least in part by regulatory incentives such as or tax credits, but as fell significantly in the 2010s and grid parity has been reached in most markets, external incentives are usually not needed.
Several hundred installations over 1 MWp have since been installed in Germany, of which more than 50 are over 10 MWp. With its introduction of feed-in tariffs in 2008, Spain briefly became the largest market with some 60 solar parks over 10 MW, but these incentives have since been withdrawn. Retrieved 5 March 2015 The USA, China, India, France, Canada, Australia, and Italy, among others, have also become major markets as shown on the list of photovoltaic power stations.
The largest sites under construction have capacities of hundreds of MWp and some more than 1 GWp.
Because of the longer shadow the array casts when tilted at a steeper angle, this area is typically about 10% higher for an adjustable tilt array or a single axis tracker, and 20% higher for a 2-axis tracker, though these figures will vary depending on the latitude and topography.
The best locations for solar parks in terms of land use are held to be Brownfield land, or where there is no other valuable land use. Even in cultivated areas, a significant proportion of the site of a solar farm can also be devoted to other productive uses, such as crop growing or biodiversity. The change in albedo affects local temperature. One study claims a temperature rise due to the heat island effect, and another study claims that surroundings in arid ecosystems become cooler.
Sometimes 'solar park' is used to describe a set of individual solar power stations, which share sites or infrastructure, and 'cluster' is used where several plants are located nearby without any shared resources. Some examples of solar parks are the Charanka Solar Park, where there are 17 different generation projects; Neuhardenberg, with eleven plants, and the Golmud solar park with total reported capacity over 500MW. An extreme example would be calling all of the solar farms in the Gujarat state of India a single solar park, the Gujarat Solar Park.
To avoid land use altogether, in 2022, a 5 MW floating solar park was installed in the Alqueva Dam reservoir, Portugal, enabling solar power and hydroelectric energy to be combined. Separately, a German engineering firm committed to integrating an offshore floating solar farm with an offshore wind farm to use ocean space more efficiently. The projects involve "Hybrid power", in which different renewable energy technologies are combined in one site.
A variant on this design is the use of arrays, whose tilt angle can be adjusted twice or four times annually to optimise seasonal output. They also require more land area to reduce internal shading at the steeper winter tilt angle. Because the increased output is typically only a few percent, it seldom justifies the increased cost and complexity of this design.
These arrays need to be spaced out to reduce inter-shading as the sun moves and the array orientations change, so need more land area. They also require more complex mechanisms to maintain the array surface at the required angle. The increased output can be of the order of 30% in locations with high levels of direct radiation, but the increase is lower in temperate climates or those with more significant diffuse radiation, due to overcast conditions. So dual axis trackers are most commonly used in subtropical regions, and were first deployed at utility scale at the Lugo plant.
Single axis tracking systems are aligned along axes roughly north–south. Some use linkages between rows so that the same actuator can adjust the angle of several rows at once.
There are two primary alternatives for configuring this conversion equipment; centralized and string inverters, although in some cases individual, or micro-inverters are used. Single inverters allows optimizing the output of each panel, and multiple inverters increases the reliability by limiting the loss of output when an inverter fails.
A key determinant of the output of the system is the conversion efficiency of the solar panels, which depends in particular on the type of solar cell used.
There will be losses between the DC output of the solar panels and the AC power delivered to the grid, due to a wide range of factors such as light absorption losses, mismatch, cable voltage drop, conversion efficiencies, and other parasitic losses. A parameter called the 'performance ratio' has been developed to evaluate the total value of these losses. The performance ratio gives a measure of the output AC power delivered as a proportion of the total DC power which the solar panels should be able to deliver under the ambient climatic conditions. In modern solar parks the performance ratio should typically be in excess of 80%.
The plant owner is an electricity generator. Most solar power plants today are owned by independent power producers (IPP's), though some are held by investor- or community-owned utilities.
Some of these power producers develop their own portfolio of power plants, but most solar parks are initially designed and constructed by specialist project developers. Typically the developer will plan the project, obtain planning and connection consents, and arrange financing for the capital required. The actual construction work is normally contracted to one or more engineering, procurement, and construction (EPC) contractors.
Major milestones in the development of a new photovoltaic power plant are planning consent, grid connection approval, financial close, construction, connection and commissioning. At each stage in the process, the developer will be able to update estimates of the anticipated performance and costs of the plant and the financial returns it should be able to deliver.
Most stations are sited within a few kilometres of a suitable grid connection point. This network needs to be capable of absorbing the output of the solar park when operating at its maximum capacity. The project developer will normally have to absorb the cost of providing power lines to this point and making the connection; in addition often to any costs associated with upgrading the grid, so it can accommodate the output from the plant. Therefore, solar power stations are sometimes built at sites of former coal-fired power stations to reuse existing infrastructure.
Solar plants' reliable solid-state systems require minimal maintenance, compared to rotating machinery. A major aspect of the O&M contract will be continuous monitoring of the performance of the plant and all of its primary subsystems, which is normally undertaken remotely. This enables performance to be compared with the anticipated output under the climatic conditions actually experienced. It also provides data to enable the scheduling of both rectification and preventive maintenance. A small number of large solar farms use a separate inverter or maximizer for each solar panel, which provide individual performance data that can be monitored. For other solar farms, Thermography is used to identify non-performing panels for replacement.
Income is affected by the reliability of equipment within the plant and also by the availability of the grid network to which it is exporting. Some connection contracts allow the transmission system operator to curtail the output of a solar park, for example at times of low demand or high availability of other generators. Some countries make statutory provision for priority access to the grid for renewable generators, such as that under the European Renewable Energy Directive.
As solar power costs reached grid parity, PV systems were able to offer power competitively in the energy market. The subsidies and incentives, which were needed to stimulate the early market as detailed below, were progressively replaced by auctions and competitive tendering leading to further price reductions.
The prices revealed by these auctions and tenders have led to highly competitive prices in many regions. Amongst the prices quoted are:
For merchant solar power stations, where the electricity is being sold into the electricity transmission network, the levelised cost of solar energy will need to match the wholesale electricity price. This point is sometimes called 'wholesale grid parity' or 'busbar parity'.
Prices for installed PV systems show regional variations, more than solar cells and panels, which tend to be global commodities. The IEA explains these discrepancies due to differences in "soft costs", which include customer acquisition, permitting, inspection and interconnection, installation labor and financing costs.
There are some exceptions where solar technologies are allocated a proportion of the RPS in what is sometimes referred to as a 'solar set aside'.
The European Union's Renewables Directive sets targets for increasing levels of deployment of renewable energy in all member states. Each has been required to develop a National Renewable Energy Action Plan showing how these targets would be met, and many of these have specific support measures for solar energy deployment. The directive also allows states to develop projects outside their national boundaries, and this may lead to bilateral programs such as the Helios project.
The Clean Development Mechanism of the UNFCCC is an international programme under which solar generating stations in certain qualifying countries can be supported.
Additionally many other countries have specific solar energy development programmes. Some examples are India's JNNSM, the Flagship Program in Australia, and similar projects in South Africa and Israel.
The electrical output of a solar park will be related to the solar radiation, the capacity of the plant and its performance ratio. The income derived from this electrical output will come primarily from the sale of the electricity, and any incentive payments such as those under Feed-in Tariffs or other support mechanisms.
Electricity prices may vary at different times of day, giving a higher price at times of high demand. This may influence the design of the plant to increase its output at such times.
The dominant costs of solar power plants are the capital cost, and therefore any associated financing and depreciation. Though operating costs are typically relatively low, especially as no fuel is required, most operators will want to ensure that adequate operation and maintenance cover is available to maximise the availability of the plant and thereby optimise the income to cost ratio.
Because of the economic background, large-scale systems are presently distributed where the support regimes have been the most consistent, or the most advantageous. Retrieved 13 April 2013 Total capacity of worldwide PV plants above 4 MWAC was assessed by Wiki-Solar as c. 220 GW in c. 9,000 installations at the end of 2019 and represents about 35 percent of estimated global PV capacity of 633 GW, up from 25 percent in 2014.
Activities in the key markets are reviewed individually below.
Geographically the states with the largest installed capacity are Telangana, Rajasthan and Andhra Pradesh with over 2 Gigawatt of installed solar power capacity each. Rajasthan and Gujarat share the Thar Desert, along with Pakistan. In May 2018, the Pavagada Solar Park became functional and had a production capacity of 2GW. As of February 2020, it is the largest Solar Park in the world. In September 2018 Acme Solar announced that it had commissioned India's cheapest solar power plant, the 200 megawatt Rajasthan Bhadla solar power park.
Solar farms in space
Technology
Solar array arrangements
Fixed arrays
Dual axis trackers
Single axis trackers
Power conversion
Centralized inverters
String inverters
Transformers
System performance
System degradation
The business of developing solar parks
Planning approval
Grid connection
Operation and maintenance
Power delivery
Economics and finance
Competitive energy costs of utility-scale solar
+ Competitive energy prices achieved by utility-scale PV plants in renewable energy auctions
Grid parity
Incentive mechanisms
Feed-in tariffs
Renewable portfolio standards and supplier obligations
Loan guarantees and other capital incentives
Tax credits and other fiscal incentives
International, national and regional programmes
Financial performance
Geography
China
Germany
India
Italy
Jordan
Spain
United States
Notable solar parks
+ Noteworthy solar power plants First MW plant World's largest at the time Europe's largest community-owned facility at the time Europe's largest at the time; first under FITs Briefly the world's largest America's largest at the time World's and Europe's largest at the time Oct 2018 Largest solar park in Japan Largest solar park in Iran Asia's largest at the time World's largest thin film plant. Extended to 52 MW in 2011 America's largest at the time Africa's first 10 MW+ plant World's largest at the time. Corresponds to 80 MWAC. World's largest at the time Extension takes it to Europe's largest at the time Asia's largest (outside China) at the time Becomes Europe's largest Asia's largest solar park World's largest solar plant at the time Becomes Europe's largest solar cluster Australasia's first 10 MW+ plant Tze'elim, Negev Israel 120 MW Jan 2020 Largest PV plant in Israel First utility-scale plants in South America Acquired by Westmill Solar Co-operative to become world's largest community-owned solar power station Biggest community-owned plant in USA Sheikh Zayed, Nouakchott
Largest solar power plant in Africa
World's largest solar park at the time Topaz, the Largest Solar Plant in the World, Is Now Fully Operational, Greentechmedia, Eric Wesoff, 24 November 2014 Largest in South America at the time Largest plant in Africa Phase II of 530 MW added to 320 MW Phase I (2013) makes this the world's largest solar power station Becomes largest plant in Australasia and Oceania Becomes the world's largest solar farm installation project (Longyanxia having been constructed in two phases) Largest PV plant in Europe Becomes largest plant in South America Monte Plata Solar, Monte Plata Dominican Republic 30 MW March 2016 Largest PV plant in The Caribbean. Ituverava, Ituverava, São Paulo Brazil 210 MW Sep 2017 Largest PV plant in South America Bungala, Port Augusta, SA Australia 220 MWwatt-peak AC Nov 2018 Becomes Australasia's largest solar power plant Noor Abu Dhabi, Sweihan, Abu Dhabi United Arab Emirates 1,177 MWwatt-peak Jun 2019 The largest single solar power plant (as opposed to co-located group of projects) in Asia and the world. Cauchari Solar Plant, Cauchari Argentina 300 MW Oct 2019 Becomes South America's largest solar power plant Benban Solar Park, Benban, Aswan Egypt 1,500 MW Oct 2019 Group of 32 co-located projects becomes the largest in Africa. Bhadla Solar Park, Bhadlachuhron Ki, Rajasthan India 2,245 MW Mar 2020 Group of 31 co-located solar plants reported to be the largest solar park in the world. Largest solar park in Algeria Largest solar park in North America Largest solar park in Turkey Núñez de Balboa solar plant, Usagre, Badajoz Spain 500 MWwatt-peak AC Mar 2020 Overtakes Mula Photovoltaic Power Plant (450 MWAC installed three months earlier) to become Europe's largest solar power plant. TTC Phong Dien Vietnam 35 MW Sep 2018 First solar power plant built in Vietnam.
See also
External links
|
|